Although it may have been possible to tighten up this Schedule by a few days, it is not at all a bad record for a City with limited man power and equipment and crews whe also have maintenance responsibliities ongoing during their construction responsibilities. The financial record, tar from showing inefficiencies, shows that this project was done extremely efficiently. Our total cost for the project, including estimated 8.C. Hydro costs which have not yet been finalized, is $240,902.00. This compares with a cost of $334,000 if we had used the same unit prices as we did tor the Broadway contract. That is a reduction of 28% over our tendered prices for Broadway. You may recall that Cewe's bid on the Broadway contract was only {5% below our tendered price. it is therefore obvious that even though we have had a 2% wage increase this’ year we were still able to undercut Cewe'ls 1982 unit prices. : : ; | am extremely. proud of the effort and cooperation shown by our crews and foremen. in achieving this remarkable result. They have worked very hard In order to -Try to overcome the stigma usually associated with municipal employees’ and have shown that they are as good and efficient as anyone. - Far. trom criticizing, | would. think it would be in order for Council to. extend commendations. to our crews and foremen. FE. Peters., P. Eng.) City Engineer ToT cerned te ee NEE an ag Se RE AO petemet tie estes Se aN hs sit cnn aA vata aabeowN Me zene» en reaming. |