January 4, 1991 The Corporation of tne City of Port Coquitlam 3 4.0 SCHEDULE Following receipt ct authorization to procead Associated Engineering would be able to complete the Maple Creek ‘nternal drainage study within five weeks. PERSONNEL Associated Engineering fas an experienced team of professional engineers and tecnnical specialists with extensive experience ‘4 dyking, flood control and storm water management. ine starf has been selected for their rachnical expertise, knowledge of Jocal conditions, and experience in similar projects successfully completed for the Department of Public Works, the Ministry of Environment, and several other Districts, Cities and Municipalities. The key members of the project team and their role in the project +s cutlined below. Detailed resumes follow. Project Manager: K.R- Rudd, P.Enq. Kerry Rudd will be responsible for the overall execution of the project. He will serform the duties of the project manager and will provide and coordinate the general engineering services. Project Engineer: 5s Gunadasa, P.End. Mr. Gunadasa will perform the duties of project engineer and wiil assist in developing design criteria. Mr Gunadasa will provide technical review services throughout the project. Desian Engineer: J.H. Van der _Eerden, P.Eng. John Van der Eerden will act as design engineer and will be responsiGie For modelling the storm water system, determining the deficiencies in the system and the pumping/storage requirements in Maple Creek. FEES Associated Engineering proposes so complete the services required this assignment for a fixed fee of $7,875.00. This ree includes labour, disbursements, computer charges, and the applicable Goods Services Tax. “TTEM ASSOCIATED ENGINEERING